The concrete placing boom is divided into short parts, the range is between 12 meters and 45 meters, mainly used in the construction of large Bridges, the concrete is exported from the drag pump to the distributor for distribution, and the concrete is transported to the designated work surface.

12m fabric bar adopts rotary, arm frame fabric structure, the fabric range can reach 690 square meters, equipped with 125mm conveying pipe, 360 degrees rotation, manual operation of the whole machine. It has the characteristics of simple structure, strength, rigidity and reliability, simple operation, flexibility, convenient maintenance, etc., and can be widely used in the concrete pouring project of civil and industrial buildings.

3_副本1.jpg

1, when the wind speed exceeds 13.8 meters/second (six wind), it is strictly prohibited to work. When the wind speed exceeds 7.78 m/s (fourth level wind), it is strictly prohibited to install and disassemble the cloth machine and climb inside.

2, the distributor should maintain a certain safe distance from high-voltage lines and electrical appliances.

3, the end of the pouring hose must be tied with safety rope, do not use the length of more than 3 meters of the end hose pouring, do not insert the hose into the poured concrete, in strict accordance with the scope of the cloth machine work.

4, when the cloth machine is working, no one is allowed to stand under the boom.

5, the hydraulic system pressure shall not exceed 25Mpa.

6. It is strictly prohibited to open the pipe joint when there is pressure in the conveying pipe. 7. It is strictly prohibited to remove the end hose and connect the boom with another rigid conveying pipeline.

8. During the rotation process, it is strictly prohibited to brake or do reverse operation when the whole machine is not stopped. The joint hoop at the turning point should not be fixed too tight to ensure flexible rotation, and the rotary joint hoop should be cleaned and lubricated once per shift.

9.repair or maintenance, should be cut off the ground power supply, no live repair and maintenance.

      10. At the end of the work, the boom must be closed, the safety hook must be hung, the big arm must be placed horizontally, and the ground power supply must be cut off.